WALLACH, Circuit Judge.
Before the March 2003 invasion of Iraq, Kellogg Brown & Root Services, Inc. ("KBR") entered into multiple contracts with the United States Army for the provision of dining facility ("DFAC") services in Iraq. The contract at issue in this case was for DFAC services at Camp Anaconda ("Anaconda"), one of the largest United States military bases in Iraq at the time. In August 2003, KBR subcontracted with Tamimi Global Company, Ltd. ("Tamimi") to provide DFAC services in Anaconda. As troop levels increased, the Defense Contract Auditing Agency ("DCAA") engaged in audits of multiple DFAC subcontracts. With respect to Anaconda, the DCAA ultimately concluded that KBR had charged the Government $41.1 million in unreasonable costs for services provided from July 2004 to December 2004 and declined to pay that amount to KBR.
KBR sued in the United States Court of Federal Claims, alleging the Government unreasonably withheld the suspended $41.1 million. The Government brought multiple counterclaims, including a claim under the Anti-Kickback Act ("AKA"). The Court of Federal Claims held that KBR was entitled to $11,460,940.31 in reasonable costs. The court dismissed the majority of the Government's counterclaims, but awarded $38,000.00 to the Government on its AKA claim.
KBR appeals the Court of Federal Claims's calculation of reasonable costs, and the Government cross-appeals the court's decision with respect to its counterclaims.
Because the Court of Federal Claims did not clearly err in its calculations, we affirm its determination of cost reasonableness of the contract at issue. Additionally, we affirm the dismissal of the Government's Special Plea in Fraud and False Claims Act claims and the denial of the Government's common-law fraud claim. However, because the Court of Federal Claims improperly calculated KBR's base fee and erred when it determined that the actions of KBR's employees should not be imputed to KBR for purposes of the Government's AKA claim, those claims are reversed and remanded for further proceedings.
On December 14, 2001, the Army awarded the Army Logistics Civil Augmentation Program ("LOGCAP") Contract No. DAAA09-02-D-0007 ("LOGCAP III") to Brown & Root Services, which was then novated and transferred to KBR on August 1, 2003.
After the main contingent of ground troops began the invasion of Iraq from Kuwait on March 20, 2003, the Army began to focus on establishing dining facilities throughout Iraq, requiring KBR to establish the capacity to serve hot food to thousands of troops in a multitude of camps, well beyond that envisioned in the contract.
The typical competitive bidding process KBR used to award subcontracts was burdensome and time-consuming in light of the Army's rapidly increasing demands. In June of 2003, KBR personnel began to create an alternative system of "master agreements." This allowed KBR to establish agreements with certain subcontractors before an Army directive was issued and abbreviate the procedural process of procuring subcontractors, thus enabling KBR to perform more quickly. The board deciding which subcontractors should receive master agreements had six members, including KBR's Regional Food Service Manager for Iraq and Kuwait, Terry Hall, and his Deputy, Luther Holmes. One of the subcontractors KBR approached to enter into such a master agreement was Tamimi.
From April 2003 to January 2004, Mr. Hall and Mr. Holmes received multiple kickbacks from Tamimi's Vice President, Shabbir Khan. KBR II, 103 Fed.Cl. at 720-23, 776.
In April 2003, Mr. Khan agreed to finance a four-day trip that Mr. Hall took to Dubai, paying for the plane ticket and giving Mr. Hall $10,000.00, which Mr. Hall and Mr. Holmes split. Mr. Hall spent the first two days of his trip conducting business, and the second two days "hav[ing]
Finally, Mr. Khan gave Mr. Hall $20,000.00 in cash in January 2004. Mr. Hall had been interested in the possibility of opening up a Golden Corral franchise after leaving the Army, and Mr. Khan's cash offer was for "exploratory" research on opening this franchise. Id. After spending approximately $7,000.00 on research for the franchise, Mr. Hall was unable to secure adequate financing and abandoned the project. He kept the remainder of Mr. Khan's money for himself.
The master agreements KBR formed with subcontractors eventually corresponded to various regions of Iraq, with different subcontractors servicing specific regions. Not long after KBR instituted its master agreement system, the Army issued a requirement for a DFAC in Kirkuk, Iraq, a region associated with subcontractor The Event Source ("TES"). However, the Government later sent a letter directing KBR to relocate this DFAC to Camp Anaconda. Although KBR initially planned to keep TES as the subcontractor on this particular DFAC, it ultimately awarded Master Agreement 3 Work Release 3 ("WR 3") to Tamimi. Mr. Hall and Mr. Holmes had strongly advocated choosing Tamimi over TES. Id. at 723.
"WR 3 provided that KBR would pay Tamimi a fixed per person/per day ("PPPD") price based upon either actual headcount of troops served at the Anaconda DFAC or the projected headcount provided by the Army, whichever was greater." Id. at 724. However, because of a confluence of factors, Tamimi began operating DFAC services at Anaconda before KBR had internally approved WR 3 or generated the necessary requisitions to pay Tamimi for its services. Id.
On September 4, 2003, the Army instructed KBR to replace two of the Anaconda DFAC facilities with new, more permanent structures; however, KBR could not seek reimbursement from the Army under LOGCAP III for this work because it was in the business of providing services and not procuring buildings. A solution was devised where Tamimi would purchase the buildings and then indirectly charge KBR for the buildings through its DFAC subcontract. Id. at 725. As time elapsed, however, the Government determined that KBR should own the facilities. As the Court of Federal Claims noted, "[t] he negotiations between KBR and Tamimi regarding the construc-construction costs of these buildings played a significant role in the present dispute." Id.
Tamimi continued to operate the DFACs at Anaconda without the benefit of a contract and without the necessary requisitions by KBR. On November 3, 2003, however, KBR issued a material requisition, pricing six months of DFAC services for all four Anaconda DFACs at $111,650,000.00. After significant negotiations, extensions, and machinations, WR 3
Despite this approval, Tamimi's prices submitted to KBR for DFAC services throughout Iraq were increasingly scrutinized; both the Army and the DCAA objected to the costs submitted. Under this scrutiny, in early — to mid-2004, KBR had begun providing brief extensions while recompeting many of its DFAC contracts.
After discussions between KBR and Tamimi, the two negotiated modifications to WR 3, with Tamimi agreeing to a retrospective overall price reduction of $16,560,000.00 among Tamimi's nine subcontracts with $4,907,319.00 to be allocated to Anaconda.
Notwithstanding those efforts, KBR internally determined to not issue payments on Tamimi's invoices because of continued doubts as to the reasonableness of the prices agreed to by Tamimi.
While negotiating the above modifications with Tamimi, KBR was also attempting to recompete the work at Anaconda. After resisting, Tamimi eventually submitted a proposal for the Anaconda DFAC services on July 31, 2004; two other vendors were also planning to submit proposals. However, while waiting for these proposals, "KBR was assessing whether it would be more beneficial — and less costly — simply to self-perform the DFAC work at Anaconda." KBR II, 103 Fed.Cl. at 734. KBR management approved the idea because it predicted self-performance would result in savings of approximately $17 million.
KBR solicited proposals from vendors for the necessary labor pool to self-perform. Difficulties quickly became apparent. The necessary labor pool was not forthcoming, in part because "certain countries were precluding their citizens from entering Iraq." Id. Because of extensive subcontractor logistical problems, unrelated to Tamimi, KBR was unable to begin self-performance and was forced to extend Tamimi's period of performance until November
These negotiations commenced on November 7, 2004, and included multiple items, in addition to the items listed above, and continued negotiations over the ownership of the new Anaconda DFAC facilities. Ms. Hayes, a Procurement Manager at Anaconda, was asked by KBR to attend and became the chief and sole negotiator in negotiations that spanned from approximately mid-December 2004 to the third week of January 2005. According to Mr. Jonas, KBR's former Vice President for Procurement Materials and Property, due to KBR's strategy of slow rolling payments, KBR owed Tamimi roughly $40,000,000.00. Ms. Hayes was unaware of this leverage and failed to use it in her negotiations.
Based on the negotiations, Ms. Hayes and Tamimi agreed to Change Order 9 to WR 3. Change Order 9 officially extended Tamimi's period of performance at Anaconda until December 31, 2005. Tamimi agreed that ownership of the new DFAC facilities transferred to KBR as of November 30, 2004. Finally, Change Order 9 reflected discounts that Tamimi conceded under Change Order 6 (approximately $4,907,319.00) plus another $22,721,827.54 in discounts; therefore, the original WR 3 pricing had been reduced by a total of $27,629,146.50 from March 2004 through December 2004.
As per Change Order 9, Tamimi agreed to the following invoice amounts from March through December 2004:
KBR II, 103 Fed.Cl. at 741 n. 9 (emphasis added). These numbers reflected the negotiated solution to the DFAC ownership dispute, with the amortization of the facilities spread over all of the months until November 30, 2004, when Tamimi agreed that ownership transferred to KBR. Additionally, the cost of food was included for the first two months when Tamimi was still providing food.
In October 2003, over a year before KBR and Tamimi began negotiations for Change Order 9, the DCAA began questioning
In mid-2004 the Army formed the Special Cost Analysis Team ("SCAT") to perform "an in depth study of DFAC costs and issues." Id. at 742 (internal quotation marks and citation omitted). The leader of the SCAT effort was Lynn E. DeRoche, an official with the U.S. Army Tactical Command, who began working with KBR to resolve the boots-through-the-door issue. On March 31, 2005, KBR and the Government entered into the Global DFAC Settlement to resolve this controversy. "The Government offered KBR an overall decrement of $55 million on costs invoiced under one of the task orders from September 2003 through February 2004, which KBR accepted." KBR II, 103 Fed. Cl. at 743. However, the site-specific reasonable amount for Camp Anaconda was calculated to be greater than the amount that KBR had invoiced in subcontract costs at the site. "Thus, none of the $55 million decrement was allocated to the subcontract agreement for DFAC services at Anaconda." Id.
The work of SCAT was ongoing. On July 8, 2005, Ms. DeRoche authored the Price Negotiation Memorandum, a summary of the negotiations between KBR and the Army and the Government's position on the Global DFAC Settlement. One paragraph of the summary dealt specifically with costs at a group of Tamimi-run dining facilities that included Anaconda during the March through June 2004 period included in Ms. Hayes's negotiations. The memorandum states:
J.A. 5592.
Although KBR and the Army issued modifications implementing the Global DFAC Settlement, difficulties with Anaconda continued. On July 19, 2006, the DCAA "issued a preliminary findings report regarding DFAC services at Anaconda that questioned $44.8 million in KBR costs." KBR II, 103 Fed.Cl. at 744. Ultimately, DCAA determined $41.1 million to be unreasonable overcharges. After KBR submitted a claim to a contracting officer for the suspended $41.1 million, and while the contracting officer's decision was forthcoming, KBR commenced suit in the Court of Federal Claims on June 2, 2009.
KBR brought this suit pursuant to the Contract Disputes Act, 41 U.S.C. § 7101, et seq., alleging that the Army had unreasonably withheld money from KBR when it challenged approximately $41 million in costs and markups associated with the Camp Anaconda dining facilities for July through December 2004.
As the case progressed, the Government brought counterclaims centered upon Mr. Hall and Mr. Holmes's acceptance of kickbacks from Mr. Khan. The Government sought the forfeiture of KBR's claims pursuant to a Special Plea in Fraud, 28 U.S.C. § 2514, penalties under the AKA, 41
Following a ten-day bench trial, the Court of Federal Claims determined that $11,460,940.31 of the direct costs KBR sought were "reasonable" and thus reimbursable pursuant to FAR § 31.201-3. Together with overhead costs and general and administrative expenses, the court awarded a total of $11,792,505.31 plus interest. KBR II, 103 Fed.Cl. at 780.
This calculation was based on a rate of $6,085,825.43 per month. This monthly rate was the price negotiated by Ms. Hayes for the month of December 2004 and was "the first month that Ms. Hayes negotiated that did not, facially, include any facilities amortization." Id. at 770.
The court also awarded the Government $38,000.00 on its AKA counterclaim, but denied the Government's common-law fraud claims. Id.
Both parties appealed. This court has jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
This court reviews legal conclusions of the Court of Federal Claims without deference and its findings of fact for clear error. Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1373 (Fed.Cir. 2005). Contract interpretation is a question of law, which we review de novo. Sevenson Envtl. Servs., Inc. v. Shaw Envtl., Inc., 477 F.3d 1361, 1364-65 (Fed. Cir.2007).
KBR appeals the Court of Federal Claims's determination of reasonable fees and the calculation of KBR's base fee. We address each argument in turn.
Both parties agree that KBR is entitled to be reimbursed only for its "reasonable" costs under LOGCAP III. They also agree that LOGCAP III incorporated, by reference, the cost principles in the FAR and that FAR § 31.201-3 (codified at Title 48 of the Code of Federal Regulations) governs the assessment of the reasonableness of KBR's costs. That provision states that a cost is reasonable "if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in
FAR § 31.201-3(b).
KBR admits that the language above "emphasizes its nonexclusivity, saying reasonableness `depends upon a variety of considerations and circumstances, including' but not limited to those listed in the regulation." KBR Reply Br. 14 (emphasis in the original). Notwithstanding, KBR's core argument is that the Court of Federal Claims committed legal error by "appl[ying] an improper standard for reviewing the reasonableness of costs under the Contract Disputes Act...." KBR Br. 29. According to KBR, "cost-reimbursement contracts require only that the contractor gives its `best efforts' when performing, and its costs are payable absent gross misconduct" or "absent arbitrary action or a clear abuse of discretion." Id. at 32.
KBR's suggested standard of review finds no support in the text of section 31.201-3 or our precedent. Section 31.201-3 of the FAR affords the reviewing officer or court considerable flexibility in assessing the reasonableness of costs. The words "arbitrary," "gross negligence," and "willful misconduct" do not appear in the text. Our prior authority on cost reasonableness is contrary to KBR's position. In Boeing North American, Inc. v. Roche, this court reasoned that a cost could be "unreasonable" under section 31.201-3 when "the contractor overcharge[d] the government for the materials." 298 F.3d 1274, 1281 (Fed.Cir.2002). Absent from the court's example was any suggestion that the "overcharge" must be based on gross negligence or arbitrary behavior. Although evidence of willful misconduct, gross negligence, or arbitrary conduct could well provide a basis for a contracting officer or court to disallow costs under the regulation, such evidence is not required. KBR offers many pages of non-binding law to illustrate the amount of discretion courts have afforded to contractors.
Rather, the Court of Federal Claims applied the correct standard articulated by FAR § 31.201-3, and its analysis was consistent with the regulation's admonition that the reasonableness of specific costs "must be examined with particular care" when the costs incurred "may not be subject to effective competitive restraints." FAR § 31.201-3(a).
In addition to arguing that the Court of Federal Claims employed the wrong standard, KBR argues at length that the court
Cost reasonableness "is a question of fact." Gen. Dynamics Corp. v. United States, 410 F.2d 404, 409 (Ct.Cl. 1969). The court will overturn factual determinations only when they are clearly erroneous. See Ind. Mich. Power Co., 422 F.3d at 1373. The standard for assessing reasonableness is flexible, allowing the Court of Federal Claims to consider many fact-intensive and context-specific factors. See FAR § 31.201-3. The Court of Federal Claims's two opinions total roughly 150 pages, and comprehensively articulate the court's assessment of the cost reasonableness of the Tamimi subcontract from July 2004 to December 2004. We address each of KBR's specific arguments in turn.
The Court of Federal Claims found that KBR's summer 2004 effort to end Tamimi's involvement by self-performing dining services was "disastrous." See KBR II, 103 Fed.Cl. at 752, 758. KBR argues that this was reversible error since the Court of Federal Claims supposedly focused on the outcome of KBR's decision to self-perform, not its reasonableness ex ante. KBR Br. 40. KBR argues that this "error unquestionably infected the court's assessment of the reasonableness of all KBR's June-December 2004 prices." Id. at 43 (emphasis in original).
Contrary to KBR's characterization, the Court of Federal Claims did not conclude that KBR's costs were unreasonable based solely on KBR's failed self-performance. Rather, it adopted KBR's urging at trial that reasonableness must be determined in context, not based on standards for "conference room" contracting. KBR II, 103 Fed.Cl. at 751. The Court of Federal Claims agreed with KBR that "costs need to be reasonable, not in a vacuum, but in the context of the events in which they arose." Id. But, it cautioned KBR that consideration of all of the circumstances cut both ways: "KBR cannot now point to a deficit in bargaining power and contend that its weakened state entitles it to greater latitude" because a "contractor may not itself manufacture — or in this case exacerbate — a situation that leads to higher costs for the Government...." Id. at 752. Here, the Court of Federal Claims found that KBR was in a weak position with Tamimi, which stemmed from KBR's own conduct, including "fail[ure] to negotiate prices prospectively" and its "attempt to self-perform the work at Anaconda." Id. at 758.
These observations did not end the Court of Federal Claims's analysis. Even in its weakened position, KBR failed to act prudently to improve its leverage: "the court finds that the prudent business person would have seized any available advantage," which for KBR was $40 million in withheld funds that Ms. Hayes, KBR's negotiator, did not know about or use to KBR's advantage. Id. The subsidiary finding, that KBR's disastrous self-performance
Additionally, even if there had been an infirmity in the Court of Federal Claims's discussion of self-performance, self-performance was only one of numerous findings supporting the Court of Federal Claims's reasonableness determination. See FAR § 31.201-3(b) (providing that reasonableness is determined based "upon a variety of considerations and circumstances"). Finally, KBR's self-performance argument attacks the Court of Federal Claims's weighing of the evidence, which this court will rarely disturb. See Pacific Gas & Elec. Co. v. United States, 668 F.3d 1346, 1353 (Fed.Cir.2012) (weighing of evidence is "within the special province of the trial judge") (internal quotation marks and citation omitted).
Similar to its argument above, KBR also contends that the Court of Federal Claims impermissibly "second-guessed" KBR's negotiations with Tamimi. KBR Br. 43-48. KBR argues that the court failed to give the proper weight to this "arm's length bargaining" and how such bargaining supports a determination of reasonableness. Id. at 43 (citing FAR § 31.201-3(b)(2)). KBR argues that the Court of Federal Claims's assessment of these negotiations runs afoul of both the "business judgment rule" and the requirement that the court look to management collectively, not to the actions of individual employees. Id. at 44, 46-47.
KBR analogizes its requested standard, the "business judgment rule," to "its corporate-law analogue," which restricts courts from imposing liability "`in the absence of a showing of abuse of discretion, fraud, bad faith, or illegality.'" Id. at 36 (quoting In re Bal Harbour Club, Inc., 316 F.3d 1192, 1195 (11th Cir.2003)). Similarly, Amici Curiae the Professional Services Council and the National Defense Industrial Association argue that the Court of Federal Claims applied the wrong standard but do not urge the extreme standard argued by KBR. Amici Curiae offer instead that "what a contractor must prove, and what the [Court of Federal Claims] or [Board of Contract Appeals] must determine de novo, is whether any prudent businessperson in the contractor's position would have incurred the disputed cost." Amici Curiae Br. 8, 10 (emphases in original). As stated above, the Court of Federal Claims employed the correct standard to determine cost-reasonableness.
FAR § 31.201-3(a) requires the court to examine the reasonableness of a contractor's actions to ensure that those actions result in costs that do not exceed "that which would be incurred by a prudent person in the conduct of competitive business." A trial court's review is not restricted to only "management" actions. If a contractor acts primarily through one employee, manager or not, that employee's actions may well be a focus of the reasonableness inquiry.
KBR again appears to contest the trial court's weighing of the evidence and its assessment of KBR's witnesses. "[I]n reviewing factual findings under the clear error standard, this court `gives great deference to the [trial] court's decisions regarding credibility of witnesses.'" Medichem, S.A. v. Rolabo, S.L., 437 F.3d 1157,
The Court of Federal Claims found the agreement arising from Change Order 9 was unreasonable, based in part on its determination that KBR's negotiator, Ms. Hayes, failed to leverage withheld funds, did not set goals for the negotiation, and could not justify the prices. Ms. Hayes's testimony did not convince the court otherwise. Rather, it found that "the enthusiastic endorsement of Ms. Hayes by Mr. Jonas and plaintiff's counsel was borne out by neither her testimony nor the record of her negotiations that she included in her Negotiation Memorandum dated March 29, 2005. Her testimony was in the nature of summations on the topics, flavored with anecdotes." KBR II, 103 Fed.Cl. at 736 (internal citation omitted). KBR argues the court improperly "gave no weight" to the fact that Change Order 9 arose from an arm's-length negotiation. See KBR Br. 43. The court's credibility determinations and extensive assessment of the Change Order 9 negotiations are not clearly erroneous.
KBR contends that the Court of Federal Claims failed to consider the Army's directives in evaluating reasonableness. KBR Br. 48-51. According to KBR, although the Court of Federal Claims "recognized that the Army had told KBR that it was imperative for troop morale that soldiers in the field have hot, freshly prepared meals," the Court of Federal Claims "refused to weigh the urgency of the action — and the risk of non-performance... — in evaluating the reasonableness of the prices negotiated...." Id. at 48 (emphasis in original).
KBR correctly notes that the FAR instructs "`contractor's responsibilities to the Government'" to be considered in evaluating reasonableness. Id. at 48-49 (quoting FAR § 31.201-3(b)(3)). The Court of Federal Claims repeatedly considered all the circumstances, including the Army's directives and the fact that the costs were incurred in a demanding war-time environment. See KBR II, 103 Fed.Cl. at 752 (noting "the Army placed great demands on KBR at the outset of the war" and "the urgent need to provide many services in many locations for the Army"); id. (noting that the Army "favored" Tamimi); id. at 751 (concurring that KBR "need[ed] to fulfill the demands of the Government in performing under LOGCAP III"); id. at 752-53 (noting costs were incurred from a war "initially conducted as a contingency operation ... that became a sustained effort"); id. at 753 (recognizing that costs "were impacted by fluctuating projections for the number of troops on the ground"); id. (stating that costs "were driven by the singular goal of putting DFAC facilities in place to offer warm meals to the troops by July 4, 2003"); id. at 726-27 (acknowledging that the "constantly changing demands required by the Army's effort were foreseeable to neither the Army nor to KBR").
The Court of Federal Claims's consideration of that evidence and assessment of the Army's directives was not clearly erroneous.
KBR argues that the Court of Federal Claims incorrectly adopted the December 2004 pricing as the amount reasonably supportable, arguing that the Court of Federal Claims conflated reasonable cost
The Court of Federal Claims was within its discretion in finding that KBR failed to prove that its costs were reasonable. KBR declined to present independent evidence of the reasonableness of the facilities costs (or any other component of the challenged costs). KBR II, 103 Fed.Cl. at 752. The Court of Federal Claims was "confident" of the evidence that KBR had paid "most" of the expense of the facilities to Tamimi by July 2004 (i.e., before the period of costs at issue in this lawsuit). Id. at 770. It seems that KBR seeks a presumption that it is entitled to reimbursement simply because it incurred facilities costs. It is not. See FAR § 31.201-3(a) (providing that it is the contractor's burden to prove the reasonableness of costs and that "[n]o presumption of reasonableness" exists).
Similarly, the Court of Federal Claims's decision to base its calculation on the negotiated December 2004 pricing is not clear error. FAR § 31.201-3, which provides the standard for determining reasonableness, affords the Court of Federal Claims considerable discretion in determining whether a cost is reasonable and therefore allowable. The Court of Federal Claims used Tamimi's July 2004 competitive bid proposal as a guide for its reasonableness analysis, even though it "was not the lowest of the bids to be received in response to the July 2004 solicitation." KBR II, 103 Fed.Cl. at 770.
KBR argues that a one-paragraph "admission" in the Price Negotiation Memorandum should constitute compelling evidence of the reasonableness of the prices at Camp Anaconda.
According to KBR, "[t] he court's erroneous fee calculation is a second independent basis for reversal." KBR Br. 59. The Court of Federal Claims awarded KBR a base fee calculated as 1% of the total amount of direct costs it awarded as reasonable ($11,460,940.31), or $114,609.40. KBR II, 103 Fed.Cl. at 780. According to KBR, however, because the LOGCAP III contract called for a fixed-base fee by which KBR would receive "1% of all fee-bearing costs," J.A. 5105 (emphasis added), that fixed base fee remains the same regardless of the costs KBR actually incurred, whether reasonable or not. KBR Br. 59.
It seems the Government agrees: "The base fee, as KBR correctly argues, is owed to it for negotiated estimated costs." Gov't. Br. 77 (citing KBR Br. 60). However, the Government argues, somewhat confusingly, that because there was "no evidence presented that KBR will not be paid the balance of the base fee that had been calculated based upon its estimated costs on contract close-out," this court has no basis "to make such an award at this appeal." Gov't. Br. 77-78.
KBR responds that "the government provides no reason KBR must wait until LOGCAP's conclusion to receive the fee it admits is rightly due for services performed nearly a decade ago, or why this Court must leave a flawed judgment intact." KBR Reply Br. 23.
The record shows that the base fee is to be calculated as follows:
J.A. 5105. The Court of Federal Claims incorrectly calculated the base fee to be awarded, and that determination is reversed and remanded with instructions to calculate the fee consistently with this opinion.
Turning to the Government's cross-appeal, the Government argues that the subcontract at issue was fraudulent from its inception and that the subcontract "could never have been awarded without the acquiescence of KBR's corrupted Food Services managers, who also intervened on Tamimi's behalf when KBR's subcontract administrator decided to award the Camp Anaconda DFAC subcontract to one of Tamimi's competitors." Gov't. Br. 21. KBR responds that the Court of Federal Claims "correctly rejected the government's `relentless efforts to shoehorn' this contract dispute into the rubric of fraud, seeking to recoup hundreds of millions of dollars for fully — and successfully — performed services based on `taint' allegedly caused by $38,000.00 in kickbacks to two `mid-level' employees." KBR Reply Br. 9 (quoting KBR II, 103 Fed.Cl. at 771).
"This court ... reviews de novo a dismissal for failure to state a claim pursuant to Rule 12(b)(6) of the Court of Federal Claims, just as it does dismissals under Federal Rule of Civil Procedure 12(b)(6)." Laguna Hermosa Corp. v. United States, 671 F.3d 1284, 1288 (Fed.Cir.2012). "A complaint must be dismissed under Rule 12(b)(6) when the facts asserted do not give rise to a legal remedy or do not elevate a claim for relief to the realm of plausibility." Id. (internal citations omitted). In deciding a motion to dismiss, the court must accept well-pleaded factual allegations as true and must draw all reasonable inferences in favor of the claimant. Lindsay v. United States, 295 F.3d 1252, 1257 (Fed.Cir.2002).
Following a trial, we review the factual findings of the Court of Federal Claims for clear error and its legal conclusions de novo. Am. Pelagic Fishing Co., L.P. v. United States, 379 F.3d 1363, 1371 (Fed.Cir.2004).
The forfeiture statute provides that:
28 U.S.C. § 2514. To prevail, the Government must prove its allegations by clear and convincing evidence. UMC Elecs. Co. v. United States, 249 F.3d 1337, 1338-39 (Fed.Cir.2001).
This court has held that to prevail on a counterclaim alleging fraud under 28 U.S.C. § 2514, the challenger is required to "`establish by clear and convincing evidence that the contractor knew that its submitted claims were false, and that it intended to defraud the government by submitting those claims.'" Daewoo Eng'g & Constr. Co. v. United States, 557 F.3d 1332, 1341 (Fed.Cir.2009) (quoting Commercial Contractors v. United States, 154 F.3d 1357, 1362 (Fed.Cir.1998)); accord Glendale Fed. Bank, FSB v. United States, 239 F.3d 1374, 1379 (Fed.Cir.2001). "[F]orfeiture under 28 U.S.C. § 2514 requires only part of the claim to be fraudulent." Daewoo Eng'g, 557 F.3d at 1341.
The Government argues that the Court of Federal Claims incorrectly held this statute inapplicable, stating that (as in the analogous FCA context), "any invoice submitted upon a fraud-tainted contract supports the finding of a `false or fraudulent'
This is an impermissibly broad reading of the law. The Court of Federal Claims correctly limited the statute:
KBR I, 99 Fed.Cl. at 501. On its face, the statute is limited to those circumstances where the Government proves fraud "in the proof, statement, establishment or allowance" of a claim at the Court of Federal Claims, not in the execution of a contract.
Statutory context confirms this reading. Alexander v. Sandoval, 532 U.S. 275, 288, 121 S.Ct. 1511, 149 L.Ed.2d 517 (2001) (beginning analysis of the statute at issue with the text and structure of the statute). The provision codified at section 2514 was part of legislation creating the Court of Federal Claims and regulating its operations and procedure. See Act of Mar. 3, 1863, ch. 92, 12 Stat. 765, 767. The surrounding provisions concern requirements for filing claims, including time limits and verification. Thus, the neighboring provisions illustrate that the forfeiture statute is best understood as a companion requirement of claims procedure rather than a catch-all anti-fraud provision. The legislation's sponsors confirmed the forfeiture statute addressed fraud by "any claimant against th[e] Government in the demand or establishment of his claim...." Cong. Globe, 37th Cong., 2d Sess. 1674 (1862) (statement of Rep. Bingham). And this court's predecessor concluded the forfeiture statute addressed "frauds committed in the proof of claims before the newly empowered Court of Claims." O'Brien Gear & Mach. Co. v. United States, 591 F.2d 666, 678 (Ct.Cl.1979).
The Court of Federal Claims correctly dismissed the Government's Special Plea in Fraud claim.
To state an FCA claim, the Government must show "(1) the contractor presented or caused to be presented to an agent of the United States a claim for payment; (2) the claim was false or fraudulent; (3) the contractor knew the claim was false or fraudulent; and (4) the United States suffered damages as a result...." Young-Montenay, 15 F.3d at 1043.
The Government argues two reasons why the Court of Federal Claims incorrectly dismissed its FCA claims. The first is that the invoices for the Camp Anaconda dining services subcontract were false or fraudulent because the subcontract itself was tainted by kickbacks. However, the Government does not argue here and did not argue below that the invoices themselves were false or fraudulent, a showing that is required for a FCA claim to be successful. As correctly pointed out by the Court of Federal Claims, "[n]o presumption applies to the FCA that would relieve defendant of its burden to plead facts supporting the elements of an FCA claim." KBR I, 99 Fed.Cl. at 510. The Government must claim the threshold requirements under the FCA, i.e., that a false or fraudulent claim was submitted and that KBR knew of its falsity. See Young-Montenay, 15 F.3d at 1043.
The Government also argues its allegations are sufficient because the invoices at issue should be presumed to be inflated by at least the amount of the kickback, if not more. Gov't. Br. 39. The Government states that "[t]here is no principled reason why the common-law presumption of price inflation should not apply to the facts alleged here." Id. at 41. Again, however, the Government offers no reason why in this particular case, the Government should be discharged from alleging the threshold requirements of an FCA claim. As the Court of Federal Claims held: "Defendant must allege facts showing that the costs actually inflated the contract price." KBR I, 99 Fed.Cl. at 513.
The AKA sets forth two separate civil remedies as follows:
41 U.S.C. § 55(a) (emphasis added). Under this statutory scheme, a "kickback" is defined, in relevant part, as any money, fee, commission, credit, gift, gratuity, thing of value, or compensation of any kind which is provided, directly or indirectly, to any prime contractor, prime contractor employee ... for the purpose of improperly obtaining or rewarding favorable treatment in connection with a prime contractor or ... a subcontract relating to a prime contract.
Id. § 52(2).
The Court of Federal Claims, in interpreting the AKA, found that a corporation can be held vicariously liable under both § 55(a)(1) and § 55(a)(2). However, it found that the KBR officials who accepted kickbacks were not sufficiently senior to warrant a finding of vicarious liability in this case. Accordingly, the court held KBR liable only for the amount of the kickback under § 55(a)(2). We address each holding in turn.
Our analysis begins with the language of the statute. Youngblood v. Sec'y of Health & Human Servs., 32 F.3d 552, 554 (Fed.Cir.1994) (citing K Mart Corp. v. Cartier, Inc., 486 U.S. 281, 291, 108 S.Ct. 1811, 100 L.Ed.2d 313 (1988)). It is a well-settled principle of statutory interpretation that a "statute is to be construed in a way which gives meaning and effect to all of its parts." Saunders v. Sec'y of Health & Human Servs., 25 F.3d 1031, 1035 (Fed. Cir.1994) (citing United States v. Nordic Vill., Inc., 503 U.S. 30, 36, 112 S.Ct. 1011, 117 L.Ed.2d 181 (1992) (noting the "settled rule that a statute must, if possible, be construed in such fashion that every word has some operative effect")).
The Court of Federal Claims correctly determined that § 55(a) of the AKA contemplates vicarious liability in both civil penalty provisions under subsections 1 and 2. Section 55(a)(1) directs that a civil penalty may be recovered from any "person," which is defined to include individuals, corporations, and other business associations. See 41 U.S.C. § 52(3). Section 55(a)(1) necessarily includes the definition of "person" and, in doing so, establishes liability for a "corporation." See 41 U.S.C. § 52(3). To hold otherwise would strip the term "person" of its plainly intended definition.
The difference between § 55(a)(1) and § 55(a)(2) is the degree of knowledge that must be proven. The former provision — which carries a higher penalty — applies if the person knowingly engages in prohibited conduct. The latter provides for strict liability against a "person" who engages in prohibited conduct.
KBR argues that this reading would render Congress's reference to acts committed by an "employee, subcontractor, or subcontractor employee," which appears only in § 55(a)(2), superfluous. Indeed, there is tension between the definition of "person" in both sections and the presence of "employee, subcontractor, or subcontractor employee" in only § 55(a)(2). The legislative history, however, clarifies the point:
132 Cong. Rec. S16,311 (daily ed. Oct. 15, 1986) (statement of Sen. Carl Levin). The distinction between the two different provisions rests on the degree of knowledge that must be proven, not the types of persons to whom the provisions apply.
After correctly determining that both sections contemplate vicarious liability, the Court of Federal Claims then found that this case was not an appropriate case for finding vicarious liability: "Section 55(a)(2) anticipates circumstances where a prime contractor's employees are accepting kickbacks for which the prime contractor should be held responsible, yet they are doing so without corporate knowledge of their activities or they occupy positions of diminished or low authority, such that an imputation of knowledge to the prime contractor would be inappropriate." KBR II, 103 Fed.Cl. at 774. The Court of Federal Claims also stated that "[a]lthough facts in this case approach the dividing line, the court rules that strict liability under § 55(a)(2) is the appropriate and sole remedy in this case." Id.
The Government on appeal seeks to hold KBR liable under § 55(a)(1) of the AKA for the kickbacks accepted by KBR's employees, Hall and Holmes.
Corporations act through their employees; the general rule is that an agent's knowledge is imputed to the principal when employees are acting with the scope of their authority or employment, absent special circumstances. See Meyer v. Holley, 537 U.S. 280, 285, 123 S.Ct. 824, 154 L.Ed.2d 753 (2003); Long Island Sav. Bank, FSB v. United States, 503 F.3d 1234, 1250 (Fed.Cir.2007) (explaining the general rule of imputation of a culpable state of mind in the context of common-law fraud). Congress is presumed to "inten[d] its legislation to incorporate" traditional rules such as these. Meyer, 537 U.S. at 283-85, 123 S.Ct. 824.
In Long Island Savings Bank, this court recognized a narrow exception — the adverse-interest exception — to the general rule that a principal is liable for the acts of his agent: when the agent's conduct is "entirely" in the agent's interest without even incidental benefit to the principal. See 503 F.3d at 1249-50. There, the agent used his position to hire a law firm in which he had a secret interest to perform legal services for his principal, a bank. Id. at 1239. This court found that, because the bank received services through the
KBR argues that a different set of rules apply here because the AKA imposes punitive liability: "`The common law has long recognized that agency principles limit vicarious liability for punitive awards.'" KBR Reply Br. 55 (quoting Kolstad v. Am. Dental Ass'n, 527 U.S. 526, 541, 119 S.Ct. 2118, 144 L.Ed.2d 494 (1999)).
KBR argues that Kolstad stands for the proposition that vicarious liability may give rise to liability under section 55(a)(1) only when the agent serves in a "managerial capacity." Kolstad involved punitive damages under Title VII for instances of intentional discrimination. It was not an AKA case, and its rule should not be extended to the AKA context for a number of reasons, not the least of which is that a "punitive" damage award is distinct from the type of damages provided by the AKA. Kolstad grounded its holding in the Restatement (Second) of Agency § 217 C (1957), explaining that the Restatement limits when "an agent's misconduct may be imputed to the principal for purposes of awarding punitive damages." 527 U.S. at 542, 119 S.Ct. 2118. However, these limits do not apply to "the interpretation of special statutes" like those giving "triple damages." Restatement (Second) of Agency § 217 C, cmt. (c) (1957). The "special statute" here, the AKA, with its double damage provision, does not involve punitive damages as that term was used in the statute at issue in Kolstad; the AKA is outside of the scope of Kolstad and the Restatement's heightened standard for vicarious liability.
Accordingly, the Court of Federal Claims's determination that Hall and Holmes's knowledge should not be imputed to KBR is reversed and remanded with instructions to calculate damages consistent with the holding that KBR is liable for AKA violations under section 55(a)(1).
This court stated in Godley v. United States, 5 F.3d 1473, 1476 (Fed.Cir. 1993):
It therefore fell to the Government to prove the causal link between the kickbacks and the contract provisions. The trial court's finding that no such causational link existed is reviewed for clear error. Ind. Mich. Power Co., 422 F.3d at 1373.
Following trial, the Court of Federal Claims found that KBR would have awarded the Anaconda subcontract to Tamimi even "absent any participation by Messrs. Hall and Holmes." KBR II, 103 Fed.Cl. at 779. The Government argues that this "but-for test, rather than a causal connection test," was incorrect and that the Court of Federal Claims found ample facts to support an overall finding of common-law fraud, such as "the factual finding that KBR employees receiving kickbacks played significant roles in the award of the Tamimi subcontract, including intervening with other KBR employees to ensure that Tamimi received the Camp Anaconda DFAC contract, rather than another contractor, as first intended." Gov't. Br. 3, 46.
The Court of Federal Claims found those facts. However, the Government does not dispute the Court of Federal Claims's overall finding that notwithstanding the kickbacks at issue, the subcontracts would still have been awarded to Tamimi. This court's precedent confirms that common-law fraud is not established simply by showing that kickbacks were paid to personnel involved in contract decision making: "Illegal acts by a Government contracting agent do not alone taint a contract.... Rather, the record must show some causal link between the illegality and the contract provisions." Godley, 5 F.3d at 1476.
Godley, on which the Government relies, Gov't. Br. 55-57, demonstrates that fraud must be a but-for cause of the outcome to satisfy the requirements of common-law fraud. There, a property owner contracted to build a post office to lease to the U.S. Postal Service. When the Government later learned a subcontractor on the project had bribed the decision maker, it sought to void the contract. Because the case was before this court on summary judgment, it was remanded since the court could not "determine whether [the] illegal conduct caused any unfavorable contract terms," equating that inquiry with "determin[ing] whether [the] illegal conduct tainted the contract." 5 F.3d at 1476 (emphasis added); accord id. at 1475 n. 1 (quoting K & R Eng'g Co. v. United States, 616 F.2d 469 (Ct.Cl.1980) (stating that contracts are "tainted by illegality" when they are "`the product of a conflict of interest'") (emphasis in original)).
The Court of Federal Claims found facts both against and supporting a finding of common-law fraud. For example, with regard to WR 3, the Court of Federal Claims found that Hall and Holmes were responsible for WR 3's price estimate and statement of work, and they overrode the initial decision of KBR's procurement authorities to award the work release to a
Unlike Godley, this case is not before us on summary judgment, and the Court of Federal Claims did determine, as a finding of fact, that the illegal conduct overall did not irreparably taint the contract, i.e., that "Tamimi would have received a Master Agreement and WR 3 absent any participation by Messrs. Hall and Holmes." Id. We discern no clear error in this determination.
Because the Court of Federal Claims did not clearly err in its calculations, we affirm its determination of reasonableness of costs. We also affirm the dismissal of the Government's Special Plea in Fraud and False Claims Act claims and the denial of the Government's common law-fraud claim. However, because the Court of Federal Claims improperly calculated KBR's base fee and erred when it determined that the actions of KBR's employees should not be imputed to KBR, for purposes of the Government's AKA claims, those claims are reversed and remanded for further proceedings.
AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
NEWMAN, Circuit Judge, concurring in part, dissenting in part.
Although the decision of the Court of Federal Claims is subject to controversy, for KBR provided substantial evidence that its arrangements with subcontractors to feed and accommodate a wartime Army were reasonable in view of the "constantly changing demands" of the Army's activities in the Iraq war, the Court of Federal Claims made a full and careful analysis.
However, unlike the panel majority, I would also affirm the trial court's ruling that the actions of KBR's employees Hall and Holmes who accepted favors totaling
As defined in the Anti-Kickback Act (AKA):
41 U.S.C. § 52(2).
Both liability levels arise under the "doctrine of respondeat superior," 132 Cong. Rec. S16, 311 (daily ed. Oct. 15, 1986) (statement of Sen. Carl Levin), whereby under general principles of agency law, principals are charged with liability of their agents' malfeasance "except where the agent is acting adversely to the principal." Restatement (Second) of Agency § 275 (1958). However, a "principal is not affected by the knowledge of an agent in a transaction in which the agent secretly is acting adversely to the principal and entirely for his own or another's purposes." Restatement (Second) of Agency § 282 (1958).
According to the majority's ruling, KBR as employer is charged with imputed knowledge of the kickbacks, and thus of liability for the double civil penalty, although it appears undisputed that KBR did not have actual knowledge. The majority states that KBR "received a benefit" from the kickbacks because Tamimi performed DFAC services under its existing contractual obligations. Maj. op. 1370. This ruling erases the distinction between the two statutory levels of liability in the AKA. An existing contractual relationship is a prerequisite for liability under the AKA definition of "kickback." See 41 U.S.C. § 52(2), supra, (defining kickback as payments etc. "in connection with a prime contract or a subcontract"); see also Black's Law Dictionary (9th ed.2009) (a "kickback" is "A return of a portion of a monetary sum received...." (emphasis added)). The majority's reasoning fails to recognize this inconsistency.
KBR acquiesced in its statutory strict liability under § 55(a)(2), for the $38,000 that the subcontractor paid to KBR employees Hall and Holmes. KBR Reply Br. 6. The Court of Federal Claims held KBR not liable under § 55(a)(1) for the doubled penalty because KBR's management had
There was no evidence that the bribes paid to Hall and Holmes were known to KBR or were of benefit to KBR. Hall and Holmes kept the entire payments for themselves, as "party money" and for sham business ventures. 103 Fed.Cl. at 721-22, 773-74. Although the government suggests that the bribe-paying subcontractor may have procured its sub-contracts at inflated prices, this did not benefit KBR. No benefit to KBR has been shown.
My colleagues have removed the distinction between the two subsections of § 55(a), by imposing the double penalty provision of § 55(a)(1) in circumstances that invoke only the single strict liability provision of § 55(a)(2). The trial court's ultimate and subsidiary factual findings on this issue are not clearly erroneous, and the Court of Federal Claims correctly limited KBR's liability to § 55(a)(1). From my colleagues' reversal of the Court of Federal Claims' ruling on this issue, I respectfully dissent.
J.A. 5592.